Prop S August Update

PROP S: District-wide improvements continue to take shape thanks to the $244 million bond issue passed by voters last summer to make our facilities safer for students and staff.
 
A number of projects were completed this summer, including:
  • FHN/Henderson’s entry drive was expanded to separate construction traffic from school traffic as part of the progress on the new Francis Howell North High School
  • FHC and Saeger’s parking lots were repaved
  • Track and parking lot replacement/renovations were completed at Bryan Middle
  • Major systems (HVAC, Boiler Loop, Electrical) were replaced at Becky-David, along with new paint, lighting and floors
While much progress has been made, Prop S work continues to be impacted by inflationary costs and manufacturing delays in the construction industry – both of which impact project budgets and timelines. As one example, security vestibule projects around the District have been impacted by COVID-related material delays in the steel and aluminum industries. Without the necessary interior and exterior doors required to complete the vestibules, some schools – including Bryan and Saeger middle schools – will start the school year with a temporary secure entrance.
 
The District Facilities Committee continues to monitor costs and material delays and make adjustments to Prop S plans where necessary. Stay informed about Prop S projects at fhsdschools.org/props.